Case studies
What we built, and what it had to do
Each one covers the brief, what made it hard, the panel we built and what happened on site. Some customers are named with their permission; the rest are described by what they do and roughly where.
Pump control panels
About this sector →
Pump service contractor, West Sussex
Three Telemetrix panels for West Sussex County Council's landfill pumping stations
The contractor look after the pumping infrastructure at West Sussex County Council's landfill sites under a long-term asset management contract. They fitted three wastewater high-level Telemetrix panels so the council gets live status and alerts, and maintenance can be preventative rather than reactive.
Read the case study
Pump specialist, Oxfordshire
A star/delta Telemetrix panel, turned round quickly for an Oxford campus
A pumping station on a university campus in Oxford needed its control panel replaced, along with the pump and the float switches. The pump specialist specified a bespoke star/delta Telemetrix panel with remote monitoring, and the whole job, panel, floats and a new 6kW Sulzer pump, was done in a morning.
Read the case study
Pumping station specialist, South East
Telemetrix as standard across a pump service contractor's stations
The contractor refurbishes and maintains pumping stations across the South East, and now fit Telemetrix as a matter of course: three side by side at one site, four in a single week at others, six and counting. They install them and then monitor them for their clients.
Read the case study
Drainage contractor, East Midlands
A care home pumping station rebuilt from the pipework up, with Telemetrix on top
The drainage contractor stripped and rebuilt a care home's pumping station in one job: new pipework, guide rails, pumps, pedestals, chains and grease trap, finished with new Telemetrix panels so the station is monitored around the clock.
Read the case study
Pump maintenance contractor
End-of-life panel replaced at a school, floats included, in one visit
After years of maintaining a school's pumping station and advising that the control panel had reached the end of its serviceable life, the maintenance contractor replaced it with a G&G panel and new float switches in a single visit timed to suit the school.
Read the case study
Pump service contractor
An old mill's de-watering station refurbished, with alerts added
A de-watering station under an old mill, reached through a brick culvert, was cleaned out and refurbished from the pumps up. Two new pumps, new floats and a Telemetrix panel mean the next problem is a message rather than a flooded basement.
Read the case study
Pump distributor
Out with the old, in with the new: a station upgraded to Telemetrix
The distributor replaced a tired pump control panel with Telemetrix, so the station the engineer had been called out to now tells him when something is wrong.
Read the case studyBMS control panels
About this sector →
Butlins Skegness
One motor control centre for 64 motors in a water park plant room
The pool and water park plant room at Butlins Skegness needed a new motor control centre to run every pump, blower and feature from one place, with a BMS interface for the integrator's controllers. We designed and built it in Stoke-on-Trent.
Read the case study
Confidential London project
Every BMS control panel for a prestigious London building, from one supplier
The full BMS control panel supply package for a high-profile London building: every outstation and motor control panel across its plant rooms, designed, built and tested in Stoke-on-Trent and delivered to the contractor's programme. The client and project cannot be named.
Read the case study
SSE Energy Solutions
A Form 2 outdoor BMS panel on the roof in 12 working days
SSE Energy Solutions were refitting the third floor of Highgate Mental Health Hospital in London: new walls, heating, HVAC, electrical and controls throughout, with a new BMS tying into the trust's existing Trend network. The panel for it had to sit on the roof, and the only crane was coming down in three weeks.
Read the case studyPlenty of what we build never appears here, including OEM and volume programmes. If you want to hear from someone doing what you are about to do, ask and we will arrange a reference from a customer in your sector.
In their words
“It's everything you'd expect from a G&G panel. It's simple to install and easy to use. I really like the standard in-built light. It's reliable and versatile. When clients want panels on site quick, it's perfect. In short I think it's going to be a game-changer for people in the pump industry.”
“The detail, and thought that goes into making these installer and end user friendly is second to none. The best control panels we've seen, let alone had the pleasure of using. Great products.”
“The panel is very, very decent. Highly rated so far in terms of installation and setting up.”
“Normally we'd expect a 6 to 8 week lead time on a panel build. In this case it was done in 12 working days, which is a testament to G&G Controls and SSE working together.”
Got a job like one of these?
Send the spec, the pump schedule or the points list and we will tell you what we would build and what it costs.